Welcome
to the ANGOTTI PRODUCT DEVELOPMENT e-mail newsletter!
The
goal of this newsletter is to help you accelerate your
development projects by sharing many of the tips, techniques, and
strategies we've honed during three decades of providing high-tech
consulting services.
Can
you cope with the upcoming parts shortages due to the COVID19 shutdown?
Excutive
Summary
This article outlines how a company can
respond to the upcoming shortages created by the COVID19 virus that has
shut
down companies across the globe. This information is valuable as well
for other
future disasters that cause scarcity in various parts' availability.
During
shortages, even a single unavailable part can hold up completion of the
assembly of an electronic product. What will your company do to respond?
Background
The concept of JIT (Just
in Time) manufacturing is a very economically efficient way to produce
and distribute products. JIT creates a situation where there is almost
no store of parts in the parts pipeline. Also, for the last several
years, companies in their search to reduce product costs have
diversified globally to seek the lowest cost parts sources. Both of
these can create severe logjams in product availability as the
worldwide economies begin reopening after a disaster. This article
focuses on what might help with this situation when product Fabrication
and Assembly begin to ramp up.
A response to the upcoming product production ramp-up takes two forms,
what can be done for products still in design, but not yet released to
production and those that are already in production. Be sure to note
that any alterations of specified parts in the design must be done by,
or approved by, a person sufficiently skilled to assess the
substitution of the part. Many companies have formalized this process.
Smaller, less formal ones usually rely upon the design engineer to
approve these changes.
Products in Pre Release to Manufacture
First,
always minimize sole-source parts; then locate and
specify alternate source parts. See the comments in Table 1 below.
Table 1
Potential Problem Part
|
Action
|
Remarks
|
Resistors
|
Search for trusted
equivalent parts and check for compatibility cost and delivery.
|
These parts are relatively
standardized. There are numerous reliable vendors.
|
Capacitors
|
Search for trusted
equivalent parts and check for compatibility cost and delivery.
|
Compatibility is a bit
harder to achieve than for resistors. There are several critical
variables.
|
Inductors
|
Search for trusted
equivalent parts and check for compatibility cost and delivery.
|
Compatibility is a bit
harder to achieve than for capacitors. Several critical variables,
along with mechanical variations. Consider strongly dual footprint for
designs.
|
Integrated Circuits
|
Except for a few Standard
parts, these are often a single source device. Glue logic can be
substituted with parts from trusted suppliers and checked for
compatibility and cost.
|
Sometimes parts have a dual
voltage or footprint equivalents. Consider dual footprints for both
parts. Usually, dual voltage parts require testing before they are
specified.
|
Relays
|
Except for a few standard
footprint parts, these are often a single source device. Check for
substitute parts from trusted suppliers and check for compatibility and
cost.
|
Many parts have dual
footprint equivalents. Strongly consider dual footprint layouts for
both parts.
|
Custom Mechanical Parts
|
Search for and locate
second sources from a different vendor.
|
One vendor might be lower
priced and might be selected as the preferred one. If parts volume
requirements are low, this might become a significant challenge. Tight
tolerance can also introduce additional problems.
|
Note
that Altest Corporation
(www.altestcorp.com)
has a large inventory
of quality parts, which are available to supply to companies that need
them.
Products
after Release to Manufacturing
Table 2
Potential Problem Part
|
Action
|
Remarks
|
Any Part Available in
normal Distribution Channels and using the criteria discussed in Table
1.
|
Try the usual and trusted
sources such as Digikey, Mouser, Newark, Allied, etc.
|
Depending upon your
experience, consider other distribution vendors in this class.
|
Any part available in less
reliable distribution channels and using the criteria discussed in
Table 1.
|
Try first the less trusted
vendors, and then move to the “Gray Market” to find critical parts.
|
These vendors may have
higher costs for parts or be unreliable in service or shipment time.
Gray market parts sometimes are not produced by the stated manufacturer.
|
Redesign for
alternate sub-systems or parts
If you can not locate an alternative part, then
the PCB can be redesigned to hold
another part. A redesign is the most expensive way to get the
production line moving again. It also may create minor to significant
delays in getting
production ramped up. Preplanning is always superior to these
solutions. See
Table 3 below.
Table
3
Potential Problem Part
|
Action
|
Remarks
|
Specified Part is
unavailable, out of production but an alternate part package is
available.
|
Redesign of the PCB to
accommodate the new package footprint.
|
The PCB redesign typically
must be done and then tested to ensure full compatibility. Requires
access to the original layout files, or the approach can be more costly.
|
Specified Part is now
totally unavailable, and an alternate part package is unavailable. All
source design files are available.
|
Redesign from a known
starting point. This approach requires source Schematic, BOM, and
Layout files. If the device is a microcontroller, then source code is
needed.
|
The biggest concerns are
FPGA or microcontroller changes. These can become costly and require
schedule delays.
|
Specified Part is now
totally unavailable, and another part package is unavailable. Source
design files are not available.
|
Reverse engineer design
required. Very difficult If microcontroller source code is not
available.
|
A large number of concerns
that can include FPGA or microcontroller redesigns. These can become
very costly and require very long schedule delays.
|
We can help
Do you have concerns about being
ready for the upcoming
parts shortages? APD (or Altest) can provide an
alternate source for parts selection and substitution redesign
services. If you
have such a need, give us a call at 408-462-2189 , and we can
discuss your concerns. You can learn more about us at www.angotti.com .
THE NEXT NEWSLETTER
In
the next issue, I will discuss some of the benefits and tradeoffs in
using Web based tools for project management.
FEEL FREE TO FORWARD THIS NEWSLETTER TO
YOUR ASSOCIATES
If
you think this information would be valuable to others, please feel
free to forward this newsletter to your associates. I would appreciate
it if you would not alter its contents.
If
you were forwarded this e-mail, and wish to subscribe, please send an
e-mail to mailto:carl@angotti.com with SUBSCRIBE in the
Subject Heading, and I will add you to the list of subscribers.
MORE FREE MATERIAL ON PROJECT MANAGEMENT